Bridge at Lancy, Switzerland
Description
The lowering system for the railway bridge at Lancy (CEVA) was developed by Hebetec Engineering Ltd. and first time applied by Freyssinet.
The lowering / lifting system consisting of telescopic columns is laid out to execute the laborious piling works at ground level, which is a significant advantage for working safety.
The horizontal stability of the telescopic system is achieved by fixation to bridge pier.
Due to large lowering steps (270 – 360mm) rapid execution of lowering works can be achieved. A cylinder stroke of 400mm allows for the application of MegaSteel standard modules. Job Report