hebetec engineering LTD
Bergading_0.JPG
Bergading_1.JPG
Bergading_2.JPG

Moving Oil Rig Bergading at Ulsan, Korea

Description

On March 2017 the 24’000 ton weighing oil rig Bergading was shifted to load on bord of a barge and eventually put into operation in the Gulf of Thailand.

Hebetec Engineering Ltd was fully responsible for shifting works.

For the loading the oil rig was moved with strand jacks and sliding shoes with teflon inlays. Job Report

Facts

Weight 24'000 to
Moving distance 120 m

Eingesetzte Geräte

Strand jack F-1000 6 pcs
   

 